SERD started its civil construction in early January 2013 and completed ± 42 km of its access road. In 2015 SERD has completed 6 explorations drilling wells: RD-B1, RD-B2, RD-C1, RD-I1, RD-I2, RD-C2, and in 2016 completed the Feasibility Study confirming 92 MW (gross) proven reserve capacity. After successfully reaching financial close in 2018, SERD has started the development phase activities. Despite the unfavorable conditions due to Covid-19 pandemic, SERD continued the EPC works and made significant progress in construction and commissioning activities. SERD is committed to accelerate critical works and targeting COD by the end of 2021. It has been a long and challenging journey for the SERD project, and Commercial Operation of the Geothermal Power Plant for SERD with capacity of 2x49.2 MW soon becoming reality for a green energy world in Indonesia.